Septic tanks don't last forever, and they aren't always replaced like for like. In Herefordshire the usual reasons for taking one out of use are a new sewage treatment plant, a connection to the mains when a village scheme reaches the lane, or a tank that has cracked or collapsed beyond repair. Old brick and concrete tanks under period farmhouses and cottages are the most common candidates.
Whatever the reason, the job has to be done properly. An abandoned tank full of sludge is a pollution risk. A void under a lawn is a safety risk. And a buyer's solicitor will eventually ask what happened to it.
What the rules say
The general binding rules for discharges to the ground and to surface water say that when you stop using a septic tank or treatment plant, you must remove anything that could cause pollution, such as the remaining sludge. That doesn't apply if you only stop using it temporarily, for example while a property is empty.
Beyond that, gov.uk doesn't prescribe a method. The steps below are standard good practice.
When a tank is decommissioned
- Replacing with a treatment plant. The most common case, often because the old tank discharged to a ditch or the ground won't take a drainage field. See sewage treatment plant installation.
- Replacing with a new septic tank. Where the old tank has failed but the drainage field is sound or is being renewed. See septic tank installation.
- Connecting to the mains. Where a public sewer has become available. The sewerage company has to approve the connection.
- Demolition or rebuilding. Where the tank sits under the footprint of an extension or a new building.
The steps
1. Final empty
The tank is pumped out completely by a registered waste carrier, including the settled sludge and any crust. Ask for confirmation of their waste carrier registration and keep the receipt. It's your evidence that the pollution risk was removed. On narrow lanes around Peterchurch or the Golden Valley, tanker access is worth checking at this stage, because the same access will be needed for any skip or digger. See septic tank emptying.
2. Disconnect
The inlet pipe from the house is cut and redirected to the new plant or sewer connection. The outlet to the drainage field or ditch is sealed so nothing more can flow through. Redundant pipe runs are capped.
3. Remove, or break and fill
There are two accepted approaches:
- Remove the tank. Usual for plastic or fibreglass tanks, and where the ground is needed for something else, such as a new plant in the same hole or a building. The tank is lifted out once empty and the excavation backfilled.
- Break and fill in place. Common for old brick and concrete tanks, which are awkward to lift. The roof slab is broken in, the base is broken so it can drain rather than hold water, and the tank is filled with clean inert material such as hardcore, crushed stone or sand. The aim is to leave no void that could collapse later.
A plastic tank shouldn't simply be left empty in the ground. In Herefordshire's heavy clay, and in the high-water-table land along the Wye and Lugg, an empty tank can float upwards when the ground is saturated.
4. Backfill and reinstate
The hole is backfilled in layers and compacted, then topsoiled. Clay backfill settles over the first winter, so expect to top up a lawn or bed.
5. The drainage field
An old drainage field is usually left in the ground once it's disconnected. With no flow going to it, it poses little risk. It's dug out only where the land is needed or it's in the way of new work. Occasionally an existing field can serve a new treatment plant. That's only an option if it is sound, correctly sized and meets the current rules, and a percolation test and survey should come first. See drainage fields.
Safety
An old septic tank can hold hydrogen sulphide and other gases, and the roof of an old brick tank may be weaker than it looks. Nobody should climb into a tank. Once the lid is off, the opening needs to be fenced or covered at all times, especially where children or livestock are around. This is one of the reasons decommissioning is best left to people equipped for it.
Building control and paperwork
Installing a new sewage treatment system needs building regulations approval, and planning permission may also be needed. Decommissioning the old tank is normally dealt with as part of that application. If you're only taking a tank out of use, for example because you've connected to the mains, ask Herefordshire Council building control whether they need to be notified. A mains connection also needs the sewerage company's consent.
Keep a simple record for when you sell:
- the waste carrier's receipt for the final empty
- a note or photos showing whether the tank was removed or filled, and with what
- a plan showing where the old tank and drainage field were
- the building control completion certificate for the new system
- the installation paperwork and manual for any new plant
The seller's property information form asks about the drainage system, and a buyer's surveyor finding a mystery lid in the lawn will ask questions. A tidy file answers them. See selling a house with a septic tank.
Costs
As a rough guide, decommissioning an old tank on its own tends to cost somewhere around £500–£2,000 in Herefordshire. That's a hedged range, not a quote. What moves the price:
- the size and construction of the tank (a large brick chamber takes more fill than a small plastic tank)
- whether it's removed or filled in place
- access for a digger and for the tanker on narrow lanes
- the amount of fill material and whether spoil needs taking away
- whether the drainage field is removed as well
When decommissioning is part of a replacement, it's usually priced into the whole job. See septic tank replacement costs and sewage treatment plant costs. For the wider rules, see the general binding rules and the county overview.
Questions
Can I just leave the old tank in the ground?
Only once it's been emptied, disconnected and made safe. The rules require anything that could cause pollution to be removed. A void left under the garden can collapse, so tanks left in place are usually broken and filled with inert material.
Do I need to tell the Environment Agency when I stop using a septic tank?
The general binding rules don't require you to notify anyone, only to remove anything that could cause pollution. If the tank was operating under an environmental permit, contact the Environment Agency about surrendering it.
What happens to the old drainage field?
It's usually left in place and disconnected. It's only dug out if the ground is needed. Reusing it with a new plant is possible only if it's sound and meets the current rules.
Does the property being empty count as decommissioning?
No. gov.uk is clear that the decommissioning rule doesn't apply if you've only stopped using the system temporarily, such as while a house is empty.
Can the new treatment plant go where the old tank was?
Sometimes. It depends on the plant's size and depth, the ground, and the distances to the house, boundaries and watercourse. Removing the old tank first is usually easier than working around it.